How to write a quote for a garden fencing installation (with a real worked example)
A fencer I know in Leeds priced a back garden at £1,900 on a Saturday morning, 28 metres of six foot panels, and shook on it. Monday the customer said the old fence was theirs to keep out of the skip, the neighbour said the left side was actually his, and the first post hole hit a concrete footing from a shed that had been gone for twenty years. Three days became five, the skip was never on the quote, and the left side ended up being a conversation between two households that he had no business being in.
Fence prices are easy to write and easy to lose money on, because the panels are the cheap part. This guide shows how to quote a garden fence so the boundary, the old fence, the ground and the payment are all on paper before anyone digs.
TL;DR
- Measure every run, note the slope and the access, and find out who owns each boundary before you price.
- Quote the old fence removal, the skip and the concrete as separate lines from the new fence.
- Name the style, height, post type, gravel boards and timber treatment so a substitution is a decision, not a surprise.
- Use a provisional sum for hidden footings, roots and services, and write the exclusions in plain English.
- Take a deposit that covers the materials, with the balance on completion once the customer has walked the line.
Survey before you price anything
Half an hour with a tape and a notebook saves the arguments. Five things go down before a number goes on paper.
- The runs and the height. Measure each side separately and note the finished height the customer wants. Most garden fences stay at or under two metres, and next to a road used by vehicles the usual limit is one metre without planning permission. If it is a listed building or a conservation area, check before you quote. The rules are on gov.uk.
- The ground. Level, sloping or stepped. Clay, topsoil over rubble, tree roots, old footings. Push a bar in at a few spots along the line. A slope means stepped panels or a racking fence, and both take longer.
- The boundary. Who owns which side. The title deeds or the transfer plan usually show it, and there is no rule that says left or right. Ask the customer to confirm in writing that the fence is theirs and that the neighbour knows it is coming down.
- The old fence. What is there, what condition it is in, whether the posts are set in concrete, and whether any of it is being kept. Take photographs of the whole line before you touch it.
- Access and services. Can a lorry reach the garden, or does everything go through the house. Is there a drain, a water pipe or a cable near the line. If there is any doubt about buried services, find out before you dig, not after.
Then ask what the customer wants to look at. Overlap panels, closeboard, featheredge, vertical slats or a hit-and-miss design cost different amounts in materials and in time, and the cheapest answer on day one is the one that stays on the quote.
Split the quote the way the job runs
A single figure for "new fence" is quick to write and hard to defend. Break it into lines the customer can follow.
- Strip out and disposal. Taking down the old panels and posts, breaking out set concrete, and the skip or the tip run. Priced separately, always.
- Posts and concrete. Timber or concrete, size, length, and how many. State the depth they go in and whether they are set in postcrete or ballast and cement.
- Panels or boards. Style, height, number of panels, and whether they are pressure treated, dip treated or untreated. Customers think these are the same. They are not.
- Gravel boards. Concrete or timber, and whether they are included. A fence sat on the soil rots from the bottom, and a quote that skips them looks cheaper than it is.
- Fixings, caps and trim. Clips, screws, post caps, any capping rail. It is small money but it is real money.
- Labour. Days and number of people, not a vague "labour".
- Delivery. Especially if the stuff goes through the house or the road is narrow.
Put the quantities on the quote as numbers: 17 panels, 18 posts, 17 gravel boards. A customer who sees the count does not ask why the invoice has more panels than their neighbour has. If you need a refresher on turning day rates into a price, how to price a trade job covers it.
A worked example: 30 metres of back garden fence
Adam Wójcik trading as Wójcik Fencing is pricing a rear garden on a 1980s estate: 30 metres of fence along two sides and the back, level ground, access through a side gate wide enough for a wheelbarrow but not a pallet truck. The customer wants 1.8m overlap panels on concrete posts with concrete gravel boards, and the old rotten fence taken out. Two fencers for two and a half days each.
- 17 overlap panels, 1.83m wide, pressure treated, at £32: £544
- 18 slotted concrete posts, 2.4m, at £14: £252
- 17 concrete gravel boards at £9: £153
- 36 bags of postcrete at £6: £216
- Fixings, clips, caps and sundries: £60
- Skip for old fence and spoil: £180
- Delivery: £45
- Labour, 5 person-days at £200 (includes strip-out): £1,000
- Subtotal: £2,450
- Contingency and profit at 10%: £245
- Quote, rounded: £2,700 before VAT, which is £90 a metre
If Wójcik Fencing is VAT registered, VAT at 20% adds £540, so the customer sees £3,240. As far as I know fencing work is standard rated, but check the current rules on gov.uk before you put it in writing. The £90 a metre is for this garden, this ground and these materials. A sloping plot, closeboard in place of overlap panels or a long carry from the road can push it up a lot, so don't lift the figure and use it as a rate card.
Quoted the Leeds way, at £1,900, the same job leaves the fencer £800 short before anything goes wrong. Here the risk is visible: the skip, the concrete, the panel count. If the customer wants it cheaper, change the style, drop the gravel boards for timber, or keep the posts that are still sound. Don't cut the strip-out line and hope.
Exclusions and provisional sums
Write what is outside the price, in plain English.
- Hidden footings, buried concrete, rubble or large roots on the line. Price removal as an extra once you have seen it.
- Any work on a fence that turns out to belong to the neighbour, or a boundary the customer has not confirmed.
- Gates, trellis, capping rails and any change of design after acceptance, each priced in writing before you start.
- Stepping or racking on ground that is steeper than the survey showed.
- Cutting back hedges, trees or shrubs, and moving sheds, pots or anything else against the line.
- Making good lawns and borders where the barrow tracks and the spoil have been.
Then add a provisional sum for what you cannot see. Something like: "Price assumes level ground, workable soil, no buried obstructions and access for a wheelbarrow through the side gate. If the ground is different, extra work is charged at £200 a day per person plus materials at cost, agreed in writing before we carry on."
Add one line about the boundary: "Customer confirms the fence is on their land and that the adjoining owners have been told." It sounds like a small thing and it's the line that keeps you out of a dispute. If you want a template for the rest of the paperwork, the pack below has it.
Get the Get-Paid Pack, free
Four quote forms, an invoice, T&Cs, a variation order and a job sign-off form, ready for a job like this one. Replaces around £400 of solicitor-drafted templates. No card needed.
Download instantly on the next page. Written by someone who has spent years in the UK construction field.
Payment stages that match the job
A fence is a few days' work with a big chunk of the cost sitting in the timber and concrete, so you want the materials paid for before you order them. On the £2,700 example:
- £1,080 (40%) on acceptance, to cover the panels, posts, boards and the delivery.
- £1,620 (60%) on completion, after the customer has walked the line with you and the old fence is gone.
Put the percentages and the triggers on the quote. How much is fair to ask upfront is in the guide on deposits, and the thinking behind staging bigger jobs is in stage payments for trades. Send the invoice the same day you finish. If it goes unpaid, the late payment guide has the letters.
What NOT to do
- Don't price per metre from a rate card. A figure that ignores the slope, the ground and the old fence is a guess with a number on it.
- Don't start without the boundary confirmed. Taking down a fence that belongs to the neighbour turns a £2,700 job into a legal letter.
- Don't bury the strip-out in the price. The old fence, the concrete and the skip are their own line, or you will do them for free.
- Don't leave gravel boards or the treatment off the spec. It is how a cheap quote beats yours and rots in five years.
- Don't promise a start date before the materials are paid for. Timber prices move, and your deposit is what stops you funding the customer's fence.
The short version
Measure every run, check the ground and confirm who owns the boundary before you price. Put the strip-out, posts, panels, gravel boards and labour on separate lines with the quantities shown. Use a provisional sum for what is under the soil, write the exclusions in plain English, and take a deposit that covers the timber. That leaves fewer reasons for a phone call on Monday morning.
Frequently asked questions
How much does it cost to put up a garden fence in the UK?
It depends on the height, the style, the ground and whether an old fence has to come out first. The worked example, 30 metres of 1.8m overlap panel fence on concrete posts with gravel boards and the old fence removed, comes to £2,700 before VAT, or £90 a metre. Price your own job from your own measure, not from a per-metre headline.
Do I need planning permission for a garden fence?
Usually not, as long as the fence is no higher than 2 metres, or 1 metre next to a road used by vehicles, and the property is not listed or covered by a condition that removes the right. Conservation areas and listed buildings can differ. Check the current rules on gov.uk or with the local planning authority, and put the height on the quote.
Who owns the boundary fence?
There is no general rule that the left or right fence belongs to you. Ownership is usually shown in the title deeds or the transfer plan, and the T marks on those plans can point to the owner. Get the customer to confirm in writing that the fence is theirs and that the neighbour knows, before you take anything down.
Should I charge for removing the old fence?
Yes, as its own line. Taking out old panels and posts, breaking out set concrete and paying for a skip or the tip is real time and real cost. If you leave it out, you either do it free or argue about it halfway through the job.
How long does it take to fence 30 metres?
Two fencers can usually take out an old run and put up 30 metres of panel fence in two to three working days on level, workable ground. Rock, roots, heavy clay, a slope that needs stepping or poor access for materials can add a day, which is why the quote carries a provisional sum.