How to write a quote for a consumer unit replacement (with a real worked example)
A spark I know in Bristol priced a board change on a 1970s semi at £550, one day, in and out. He swapped the old rewireable fuse box for a new RCD board, switched back on, and the upstairs lights took the RCD straight out. Then the kitchen ring did the same. A borrowed neutral between the landing light and a bedroom circuit, and a nail through a cable under the bathroom floor from a plumber years ago. The customer had no heating that night because the boiler spur was on the faulty circuit, and day one became day three. The £550 never mentioned fault finding, so every extra hour turned into an argument.
A consumer unit change looks like a fixed, tidy job. The board is the easy bit. What makes or loses the money is what the new protection finds in the old wiring. This guide shows how to quote one so the testing, the faults and the paperwork are on the quote before you isolate anything.
TL;DR
- Survey before you price: the existing board, the earthing, the bonding, the tails and a quick look at the circuits.
- Quote the board, the protective devices, the bonding and the testing as separate lines, with the quantities shown.
- Carry a fixed allowance of fault finding in the price, then a clear hourly rate for anything beyond it.
- Say on the quote that the work is notifiable under Part P and that the customer gets an Electrical Installation Certificate.
- Take a deposit for the materials, with the balance on completion when the board is live and the certificate is handed over.
What to check on the survey
Twenty minutes on site saves a day of trouble. Five things go in the notebook before a number goes on paper.
- The existing board and what it feeds. Rewireable fuses, an old split-load board or a recent unit with a few circuits added. Count the circuits, note anything odd like a shower on a 30A fuse or a garage fed from a socket, and work out how many ways the new board needs with a couple spare.
- The supply and the earthing. TN-S, TN-C-S or TT. If it is TT, check the earth rod and allow for a new one if the reading is poor. Note whether there is an isolator between the meter and the board. If there is not, you either fit one or arrange isolation with the network operator, and that can take time to book.
- Main protective bonding. Is there 10mm² bonding to the gas and the water, and is it connected near where the services come in. Missing or undersized bonding is common in older houses, and it goes on the quote as its own line.
- The meter tails. Size, condition and length. Old 16mm² tails on a 100A fuse need talking about, and if the board is moving, the tails may not reach.
- A look at the circuits. If you can, take a quick insulation resistance reading on the worst-looking circuits before you quote. Old rubber cable, lighting with no circuit protective conductor, or obvious DIY in the loft all mean more risk once the RCD protection goes on.
Also check where the board sits. Under the stairs is fine, but a board that has to come out of a cupboard the customer is about to tile around, or one that has to be moved for a kitchen, is a different job. Take photographs of the board, the meter and the bonding points before you leave.
Split the quote the way the job runs
"Supply and fit new consumer unit, £600" is quick to write and hard to defend once the RCD starts tripping. Break it into lines the customer can follow.
- The consumer unit. Make, number of ways, and that it is a metal, non-combustible enclosure, which the wiring regulations have required for domestic boards since 2016.
- Protective devices. All-RCBO or dual RCD, and how many. Each circuit on its own RCBO costs more upfront and saves a lot of nuisance tripping later, so give the customer the choice in pounds.
- Surge protection. A surge protective device, unless your risk assessment under the current edition of BS 7671 says it is not needed. Put it on the quote either way so the customer can see the decision.
- Bonding, tails and earthing. New 10mm² main bonding, new meter tails or an isolator if needed, and an earth rod on a TT supply.
- Labour for the changeover. Days and people, not a vague "labour".
- Testing and certification. Testing every circuit, filling in the schedule of test results and issuing the Electrical Installation Certificate. It takes time, so price it.
- Building regulations notification. Through your competent person scheme. A small line, but it shows the work is being done properly.
Put the numbers on the quote: one 14-way board, ten RCBOs, one SPD. A customer who can see the count doesn't ask why the electrician down the road was cheaper with a smaller board and two RCDs. If you need help turning your day rate into a price, how to price a trade job covers it.
A worked example: a board change on a 3-bed semi
Adam Wójcik trading as Wójcik Electrical is pricing a board change on a 1960s three-bed semi. The old board is a rewireable fuse box with eight circuits. A previous owner added a shower and an outside socket, so there are ten circuits to carry over. The supply is TN-C-S with a 100A fuse and an isolator already fitted. Gas bonding is there, water bonding is missing. A quick insulation test on the upstairs lighting reads lower than he would like. The customer wants an all-RCBO board.
- 14-way metal consumer unit with main switch: £85
- 10 RCBOs at £22: £220
- Type 2 surge protective device: £60
- 10mm² bonding to the water, clamps, 25mm² tails and labels: £45
- Sundries, glands, blanks and the circuit chart: £25
- Labour, changeover, 1 day at £300: £300
- Testing, schedule of results and certificate, half a day: £150
- Building regulations notification through the scheme: £10
- Subtotal: £895
- Contingency and profit at 10%: £90
- Quote, rounded: £995 before VAT
If Wójcik Electrical is VAT registered, VAT at 20% adds £199, so the customer sees £1,194. As far as I know a consumer unit change is standard rated, but check the current rules on gov.uk before you put it in writing. The parts prices move around between wholesalers, and the notification fee is whatever your scheme charges, so treat those as placeholders for your own numbers.
The price includes up to two hours of fault finding. That covers most borrowed neutrals and the odd damaged cable. Anything past that is quoted at £60 an hour, agreed with the customer before he carries on. Quoted the Bristol way, at £550, the same job is £445 short before a single fault turns up, and the faults are the bit the customer pays for in arguments instead of money.
If the customer wants it cheaper, offer a dual RCD board in place of the RCBOs and show the saving. Don't drop the testing, the bonding or the SPD to hit a number.
Exclusions and the fault-finding line
Write what is outside the price, in plain English.
- Repairs to existing circuits found faulty on test, beyond the two hours of fault finding included.
- Replacing damaged or unsafe cable, accessories or light fittings found during the work. Quoted separately once seen.
- Moving the board, the meter or the supply, and any work by the network operator or the supplier.
- Upgrading the main fuse or the supply cable. That is the network operator's job, not yours.
- Making good plaster, decoration or boxing around the new board.
- Any new circuits, extra sockets or changes the customer asks for after acceptance, each priced in writing.
Then add the line that does the work: "The new board adds RCD protection to every circuit. Faults in the existing wiring that the old fuses did not detect may show up when we switch back on. Up to two hours of fault finding is included. Beyond that, work is charged at £60 an hour plus materials, agreed with you before we carry on. If a circuit cannot be made safe on the day, it will be left disconnected and labelled, and we will tell you why."
That last sentence matters. You cannot leave a dangerous circuit live to keep a customer happy, and they need to know before the day that a circuit might stay off. If you want a template for the rest of the paperwork, the pack below has one.
Get the Get-Paid Pack, free
Four quote forms, an invoice, T&Cs, a variation order and a job sign-off form, ready for a job like this one. Replaces around £400 of solicitor-drafted templates. No card needed.
Download instantly on the next page. Written by someone who has spent years in the UK construction field.
Part P, the certificate and the paperwork
In England, replacing a consumer unit is notifiable work under Part P of the Building Regulations. If you are registered with a competent person scheme, you notify it through the scheme and the customer gets a compliance certificate from building control afterwards. If you are not, the work has to go through the local authority's building control, which costs the customer more and takes longer. Wales has similar rules, and Scotland and Northern Ireland run their own systems, so check where the job is. The guide on Part P self-certification goes through the schemes.
On the day, the customer gets the Electrical Installation Certificate with the schedule of inspections and the schedule of test results. Put that on the quote in plain words, so the customer knows what they are paying for. It is also the thing that protects you if someone else touches the installation later. Keep a copy with the job, along with the photographs from the survey and any circuits you left disconnected.
Payment stages that match the job
A board change is usually one or two days, but most of the materials are bought before you start. On the £995 example:
- £300 (around 30%) on acceptance, to cover the board, the RCBOs and the SPD.
- £695 (the balance) on completion, when the board is live and the Electrical Installation Certificate has been handed over.
Don't tie the balance to the building control certificate. That arrives in the post weeks later and has nothing to do with whether the work is finished. Any agreed fault finding goes on the same final invoice, itemised. How much to ask for upfront is in the guide on deposits. Send the invoice the same day you finish, and if it sits unpaid, the late payment guide has the letters.
What NOT to do
- Don't quote a board change as a fixed price with no fault-finding line. The new protection will find what the old fuses missed, and you will pay for it.
- Don't skip the survey test. Ten minutes with an insulation tester on the worst circuits tells you more than the age of the house.
- Don't leave the bonding off the quote. Missing water bonding is common, and fitting it "while you're there" for free adds up across a year.
- Don't promise every circuit back on. If something is dangerous, it stays off, and the customer should have heard that from the quote first.
- Don't forget the notification. Unnotified work comes back when the customer sells the house, and the solicitor asks for the certificate.
The short version
Survey the board, the earthing, the bonding and the tails, and test the worst circuits before you price. Put the board, the RCBOs, the SPD, the bonding, the changeover and the testing on separate lines with the quantities shown. Include a fixed amount of fault finding, then an hourly rate for anything more, and say clearly that unsafe circuits will be left off. Notify the work, hand over the certificate and take a deposit that covers the parts. That way the RCD tripping on switch-on is a line on the quote, not a row on the doorstep.
Frequently asked questions
How much does it cost to replace a consumer unit in the UK?
It depends on the number of circuits, the type of protection, the earthing and how many faults turn up on test. The worked example, a 14-way metal all-RCBO board with surge protection, new water bonding, testing and certification on a three-bed semi, comes to £995 before VAT. Price your own job from your own survey, not from a headline figure.
Does replacing a consumer unit need building regulations approval?
In England, yes. It is notifiable under Part P. A registered competent person can self-certify and notify through their scheme, and the customer then gets a compliance certificate. Without a scheme, the work goes through local authority building control. Wales has similar rules, and Scotland and Northern Ireland have their own.
Does a new consumer unit have to be metal?
For domestic installations, the wiring regulations have required consumer units to have a non-combustible enclosure, which in practice means metal, since 2016. Check the current edition of BS 7671 and put the board type on the quote.
What happens if the RCD keeps tripping after a board change?
It usually means there is a fault on an existing circuit that the old fuses did not pick up, such as a borrowed neutral, damaged cable or moisture in an accessory. The quote should include a set amount of fault finding, an hourly rate for anything beyond it, and a line saying a circuit that cannot be made safe will be left disconnected and labelled.
How long does a consumer unit replacement take?
One electrician can usually swap a board and test it in a day on a typical house with ten or so circuits and no major faults. Missing bonding, a TT earth that needs a new rod, or faults found on test can add half a day or more, which is why the quote carries a fault-finding allowance.